|
Vietnam covers an area of 331 689 km2 in southeast Asia and
has a population of about 76 million.
Water resources
The mean annual rainfall is about 1861 mm, ranging from 1842 mm in the
north to 1880 mm in the south. Some locations receive more than 5000 mm/year.
Flow rates in the rivers are thus high, at about 10 to 90 l/s.km2.
the total average flow of all the country¡¯s rivers is about 275 000 m3/s.
A rockfill dam more than 60 m high is under construction for the Ham
Thuan/Da Mi hydro project, on the La Nga, while a 67 m-high dam is under construction for
the 720 MW Yali hydro project.
Energy and power sectors
Vietnam has abundant resources of hydropower, coal, oil and gas. Much
of the hydro potential is the central and northern region, while the oil resources are
mainly in the south.
The main sources of energy of energy in 1994 were: oil (61.8 per cent);
coal 925.5 per cnet); and, electricity (12.7 per cent). Biomass plays a very important
role in rural areas, which has resulted in severe deforestation.
The main sources of electricity production in 1996 were: hydropower (70
per cent), thermal plants (coal. Oil and gas)(13.5 per cent), gas (8.8 per cent ). Oil
(5.9 per cent )and diesel (1.8 per cent). Total electricity consumption was 12 300 Gwh.
Electricity of Viet Nam (EVVn) is in charge of energy resources , and
the construction and operation of power plants. It distributes power in the north. South
and central regions through its five regional power companies: power Companies Nos. 1, 2
and 3 respectively, the Hanoi Power Company and Ho chi Mimh Power Company. The Planning
and design of power generation Projects is carried out by Power Investigation and Design
Companies 1 and 2. Which are also under EVN. There is no private ownership of powerplants.
As a result of nearly 30 years of war. The organization and management
of the power sector need to be improved.
Vietnam began a major power sector reform in January 1995 aimed at
developing a system that would operate more efficiently, and to allow for integrated
strategic planning. As one of the steps the Government set up EVN in January 195, with a
holding company comprising 34 business units engaged in generation, transmission, and
distribution.
Electricity demand is increasing very rapidly, with increases exceeding
20 per cent/year in recent years. Chronic and severe power shortages in the south have now
been eased through the interconnection of the northern/central and southern grids.
About 51 per cent of households have an electricity supply. The per
capita electricity consumption is 149 kWh/person/year total and 53.8 kWh/person/year for
domestic consumption (1995). There is thus vast potential for increased power demand in
the future, with per capita electricity consumption expected to double in the next decade,
and with predicted annual growth rates of about 14 per cent up to 2000, reducing to around
11.5 per cent between 2001 and 2005. About 600 to 700 MW of new generation capacity will
thus need to be commissioned each year up to 2005.
To reach this targets, the Government is encouraging private investment
in the power sectors. Many new projects are planned, and restricting of the country¡¯s power industry, financial and legal
system are under way.
EVN expected total power output in 1996 to be 16.4 TWh. 35 per cent
more than in 1994, but still 1 TWh below the demand. The company aims to almost double its
production to 26 to 29 TWh/year by 2000. Demand is expected to continue to increase
considerably, possibly reaching 60 TWh/year by 2006.
Vietnam¡¯s
power sector development includes the refurbishment of existing plants, the construction
of new capacity and the conversion of existing gas turbine plants from single to combined
cycle. Among the plants scheduled for refurbishment is the Da Nhim hydro plant, and of the
new powerplants planns, son La hydro project will be the largest, with a capacity of 2400
to 3600 MW.
Private hydropower and coal-fired power projects are to be implemented,
particularly in the north of the country. The Ministry of Industry recently invited
private firms to submit proposals for BOT projects totalling 1.6 GW, and a number of
memoranda of understanding have been signed. The Ministry also expects to offer one
coal-fired project, one hydro project and four gas-fired projects, with a total capacity
of about 2000 MW, to the private sector.
It is estimated that Vietnam requires an investment of US$ 23.5 billion
between 1995 and 2010 for power sector development, two-thirds of which will be spent on
power generation projects. It is expected that half of the additional capacity will come
from BOT projects. Therefore , the Government is working hard to attract private and
foreign participation.
Hydropower development
A preliminary estimate of Vietnam¡¯s gross theoretical hydropower potential is about 300 TWh/year(34
700 MW).
The technically feasible hydro potential is estimated to be 80 to 100
TWh/year, representing about 17 700 MW. Of this, 51 TWh/year of potential is in the north,
19 TWh/year in the central regions and 10.5 TWh/year in the south. A ptreliminary estimate
of the economic hydro potential is about 18 000 MW (80 417 GWh/year).
The hydropower potential is mainly concentrated on three rivers: 6258
MW on the Da river in the north. 1485 MW on the Sesan river in central Vietnam, and 2500
MW on the Dongmai river in the south.
Vietnam has about 4600 MW of installed capacity at all of its plants,
of which 2883.5 MW is hydro capacity. About two-thirds of the powerplant capacity is in
the north, despite half of the power demand (1280 MW of 2600 MW)begin in the south. Hydro
plants generated 12 343 GWh in 1995 (83 per cent) of power production and 11 900 GWh in
1996 (70 per cent).
There is 1262 MW of hydro capacity under construction, the four largest
plants all being scheduled for completion in 1999. Yali (720 MW); song Hinh (70 MW); and
Ham thuan and Da Mi (300+172 MW). However, the Yali project could begin service by the
second half of 1998. Ham Thuan-Da Mi will be the largest hydro plant in the south of the
country. A transmission lines is to be built connecting Yali to Thailand, via Laos.
The feasibility study and preparation of tender documentation for Dai
Ninh (300 MW), in binh thuan province in the south, and now being completied by Sogreah of
France and PACIFIC Rim Power of Canada. Funding has not yeat been finalized.
Other large hydro projects planned for implementation up to 2010
include: Son La (2400 to 3600 MW); Thuong Kon Tum (260 MW); Ban Mai (350 MW); Upper Kon
tum (260 MW); Dai Thi (250 MW); An Khe (116 MW); Se San (366 MW); and, Can Don-huoi Quang
9650 MW).
Small hydro
Some 400 small hydro stations (1 to 10 MW)have been constructed, with a
total capacity of 70 MW, representing only about 3 per cent of the potential. However,
more than a third of these plants (20 MW) require renovation. For 100 kW to 1 MW plants
(500 sites), 10 MW of a potential 200 MW (5 per cent) has been developed. There are also
estimated to be 2500 possible sites for micro hydro plants (up to 100 kW).
The Government has a policy of promoting micro hydro, to improve living
standards in mountainous areas. At present, the priorities are to import low cost micro
hydro equipment, train technical personnel and transfer technology to Vietnam. Intention
co-operation is thus being strongly encouraged. Foreign funding of mini hydro schemes and
public investment is to increase, and the Prime Minister has expressed an intention to
construct up to 200 schemes with capacities of about 1 MW each. Investment would come from
international loans and with joint venture agreements for equipment manufacture.
Future outlook
The energy sector of Vietnam urgently needs to be developed. However,
the country still faces a number of problems, one which is lack of adequate capital for
investment.
Hydropower is a major priority for future years, as well as completion
of the grid interconnection program allowing for development of large hydro sites such as
the major Son La project on the Da river upstream of Hoa Binh, in the north.
The masterplan for development of hydro projects is concentrated mainly
on the Da river in the north, the Sesan river in central vietnam and the Dong Nai river in
the south, a total of about 4000 MW capacity.
|